FINAL PROJECT CLOSE-OUT
|
-
Close Out Process Begins
-
PM/CM/Other Initiates Workflow in Doc Mgmt.
-
PM or CM (Review Items have been completed)
-
Confirms that all contract change requests
have been negotiated and incorporated into change orders.
-
Confirms that all construction punchlist tasks have been completed.
-
Confirms receipt of record set / as-built drawings from contractor.
-
Confirms receipt of warranty documents.
-
Processes final payment request.
-
Email Notification Regarding Project Close-Out
-
Directors & Assoc. Vice Chancellors get notified.
-
Upload As-Built Drawings (Suzy) - Email Notification
-
Upload to ePlanRoom
-
Pictures Uploaded from Building - Email Notification
-
Sharif R.
-
Retention Kick-Off - Email Notification
-
Contracts (Retention for project documents should be started)
-
SharePoint Folder Cleanup
-
Jeanne P.
-
Review Following Documents are completed
-
CIB
-
PIF/PAF
-
Adjusted Schedule
-
Place draft CIB and 505 in SharePoint
-
Review draft CIB and 505 for Completeness
-
Assoc. Vice Chancellor Review
-
Create/Route DocuSign for CIB & 505
-
Update CIB Info in Project Website and ttach document
-
Update UCOP System with Latest Data
-
Upddated only if the project is an Approved UCOP Project
-
Accounting Review
-
Close account in Application's site/CapSTAR
-
Check on the milestone tab for "accounting close-out date"
-
SharePoint Project is moved from Active to Archive
-
Move Project to Archive
|